The welding works and the outfitting have progressed in time. On thursday 5th of Jan 2012 took therefore place the lift of deckhouse. It was attached on its fixed rubber mounts in the hull later in the same afternoon.
Now this crew transfer vessel (CTV) newbuilding Nr. 1349 will phase the final navigation outfitting. And the gripper will be lifted, bolted and connected in the bow soon as well.
Factory tests will be held later after connecting all vessel systems. Ice situation here at Turku Archipelago defines then the actual floating date and more accurate position of the technical sea trials.